Calculadoras de obra

Calculadora de block

160 bloques+ 12 bultos de mortero
Área del muro
160.00 SF
Block por SF
1.000 por SF
Blocks (8" × 18")
160 block
Peso de los blocks (40.02 lb c/u)
6,403 lb (3.20 tons)
Mortero, bultos de 80 lb
12 bultos
Grout
12.6 ft³ (0.46 CY)
Grout, bultos de 80 lb
20 bultos
Varilla
Varillas verticales #5
7 × 8' 0"
Acero vertical (con traslapes)
56.0 LF
Varillas por comprar
4 × #5 (20' 0")
Peso total
58.4 lb
Refuerzo de junta @ 16"
Hileras hacia arriba
5 hileras
Largo (hileras × largo del muro)
100.0 LF
Piezas (10' 0", traslapadas 6")
15 piezas
8" × 8" × 18"

Estos croquis son para ayudarte a pedir material y cotizar el trabajo rápido. No son planos de ingeniería ni de taller — construye siempre con los planos aprobados del proyecto.

Las franjas sombreadas son celdas con grout; las hiladas azules son vigas de amarre. Las líneas azules son las varillas verticales; las punteadas, el refuerzo de junta.

Puertas y ventanas (se restan)

Tamaño del block
Ancho del block
Tipo de block
Cara del block
Aparejo
Ajustes▾

No se agrega desperdicio a menos que lo escribas. El mortero ya incluye un poco de desperdicio (TEK 4-2A).

Ver las cuentas▾
  1. Área del muro
    A = length × height
    20' 0" × 8' 0" = 160.00 SF
  2. Block por SF
    144 ÷ (16" × face height), nominal sizes include the joint
    144 ÷ (16 × 8) = 1.000
  3. Block
    net area × per SF, rounded up
    160.00 SF × 1.000 = 160
  4. Mortero (bultos de 80 lb)
    standard units ÷ 16 per bag
    160.00 SF × 1.125 ÷ 16 = 12
  5. Grout in the rebar cells (mold-book void)
    bar locations × (height ÷ 8") courses × void per cell
    7 × 8' 0" ÷ 8" × 258.2 in³ = 12.55 ft³
  6. Block weight (normal weight, 137 lb/ft³)
    blocks × unit weight (mold book)
    160 × 40.02 lb = 6,403 lb
  7. Grout
    cells: wall SF × TEK 4-2A Table 3 ft³ per 100 SF (by width and spacing) ÷ 100; bond beams: LF ÷ LF per bag × 0.66 ft³
    160.00 SF = 12.55 ft³
  8. Vertical bars at the spacing
    wall length ÷ spacing, rounded up, + 1 (a bar at each end)
    20 × 12 ÷ 45 (in), rounded up, + 1 = 7
  9. Lap length
    bar diameter × lap diameters
    #5: 0.625 × 48 (in) = 2' 6"
  10. Vertical steel
    bars × wall height
    7 × (8) (ft) = 56' 0"
  11. #5 weight
    feet × lb per foot (ASTM A615)
    56 × 1.043 = 58.4 lb
  12. #5 stock bars
    full pieces + cut pieces packed into stock bars
    20' bars = 4
  13. Joint reinforcement rows
    height ÷ spacing, rounded up, − 1 (none in the top joint)
    8' 0" ÷ 1' 4" = 5
  14. Joint reinforcement, length
    rows × wall length
    5 × 20' 0" = 100' 0"
  15. Joint reinforcement, pieces
    per row ⌈(length − piece) ÷ (piece − lap)⌉ + 1, × rows
    3 × 5 = 15

De dónde salen los números

  • Blocks per square foot: 144 ÷ (length × height): 8" × 18" = 1.000 per SF, 8" × 16" = 1.125 per SFWorked out from the nominal face, which already includes the ⅜" joint (actual 7⅝" × 17⅝" or 7⅝" × 15⅝"). CMHA/NCMA TEK 4-2A gives 119 per 100 SF of 8" × 16" including about 5% waste: 112.5 × 1.05 = 118.1, which agrees. 8" × 18" block is the page default; it has two cells 9" apart, so grout and bars land on a 9" grid.Fuente
  • Mortar: One 80 lb bag of preblended mortar lays about 16 standard block (face-shell bedding)TEK 4-2A Table 2, a rule of thumb that already includes nominal waste. Masonry cement: 8 × 70 lb bags + 1 ton sand ≈ 240 block. Mortar use varies with the mason and the layout.Fuente
  • Block void and weight: From the supplier's mold book (Besser unit calculations): 8" × 18" hollow 504.75 in³ net, 40.02 lb normal / 29.21 lb lightweight; 75% solid 793.83 in³, 62.94 / 45.94 lbSuperior Block Corp (Brooklyn) mold book, Besser drawings: each unit's net concrete volume and weight at 100 lb/ft³ (lightweight) and 137 lb/ft³ (normal weight). Grout fills the void = W × H × L − net (the cores plus the end flanges), half of it per cell; a column of cells is the wall height ÷ 8" courses. 8" × 18" hollow (02-724817): 1,021.1 − 504.75 = 516.4 in³, 258.2 per cell. 6" 02-211431, 8" × 16" 02-726809, 10" 517602, 12" 517606; 75% solid 517599, 474106, 517604, 517608. TEK 4-2A Table 3 prints more grout per SF than these voids (e.g. 8" × 16" every cell 36.1 ft³ per 100 SF with 3% waste vs 26.9 from the void) — grout also fills the joints and spills; add waste. Sizes not in the book use TEK.
  • Wall given by area: Rebar and joint reinforcement assume a 12' high wall: length = area ÷ 12'Bars and joint reinforcement depend on the wall's length and height, not just its area. With only the area, the page takes a 12' high wall (the length is the area ÷ 12') for a first, minimal count — enter the length and height for the real wall.
  • Joint reinforcement: A row in the bed joint every 16" up the wall (none in the top joint), 10' pieces lapped 6"NCMA TEK 12-02B: "typical joint reinforcement spacing is 16 in. on center"; splices "a minimum of 6 in."; W1.7 (9 gage) is the most common wire. 10' standard pieces: Hohmann & Barnard (https://h-b.com/products/continuous-wire). Rows = ⌈height ÷ spacing⌉ − 1; length = rows × wall length (openings not taken off — a little extra); pieces per row = ⌈(length − piece) ÷ (piece − lap)⌉ + 1. Order the width for your block. Corners and tees: prefabricated pieces, count them from your drawings.Fuente
  • Grout: TEK 4-2A Table 3, ft³ per 100 SF — every cell: 6" 25.6 · 8" 36.1 · 10" 47.0 · 12" 58.9; at 48": 4.3 · 6.1 · 7.9 · 9.9 (rows for 16, 24, 32 and 40" too)TEK 4-2A Table 3 (two-core block, 3% waste), the row for your width and spacing. TEK Table 4 counts cores per bag and gives more bags than volume ÷ 0.66; the app uses Table 3 volume. Bond beams: Table 5, 80 lb bag of preblended grout ≈ 0.66 ft³ fills 2.7 LF of 6", 2.0 LF of 8", 1.6 LF of 12" bond beam. Grouting 4" block is not recommended.Fuente
  • Bar layout: Vertical: ⌈wall length ÷ spacing⌉ + 1 (a bar at each end) + 2 per opening; bond beams: bars × wall lengthGeometry only. Real bars sit in the block cells, so the spacing is a multiple of 8" and a bar can move a cell to clear an opening or a control joint. Bars at corners, wall intersections and jambs follow your structural drawings.
  • Lift bars (6'8"): Low-lift grouting: build at most 5'4", set the bars, grout, repeat — bars are spliced at each pour heightCMHA CMU-FAQ-005: low-lift sections are no taller than 5'4" and "continuity of the reinforcement is maintained by splicing between each section". 6'8" (80") is a 20' bar cut in three with no waste, short enough for the mason to lift block over. In a 4' (48") lift it sticks up 80 − 48 = 32" — a full lap for #4 (24") and #5 (30") at 48 diameters, but not #6 (36"). A new bar is set at every pour height, so pieces per location = ⌈(height − bar) ÷ lift⌉ + 1, each lapping the one below by bar − lift, with the top piece cut to fit.Fuente
  • Lap length: 48 bar diameters for Grade 60 (#4 = 24", #5 = 30", #6 = 36")The IBC 2107.2 alternative for allowable stress design, as summarized by ENERCALC: 40 diameters for 40 ksi bars, 48 for 60 ksi. The TMS 402 development-length equation (Eq. 6-1) depends on masonry strength, cover and bar size and often gives longer laps (up to 72 diameters) — use the lap on your structural drawings when it is given.Fuente
  • TMS 402 lap equation: ld = 0.13 × db² × fy × γ ÷ (K × √f′m), at least 12"; γ = 1.0 (#3–#5), 1.3 (#6–#7), 1.5 (#8+)Masonry Advisory Council summary of TMS 402. K is the smallest of the cover, the clear spacing between splices and 9 db. Not computed here — it needs f′m and cover from the design.Fuente
  • Drill-in dowels: One per vertical bar; length = embedment (4" default) + one lap above the slab or footingThe first vertical bar laps the dowel. The embedment is your engineer's or the adhesive report's number — 4" is only the default; adhesive makers list minimum embedments per bar size (e.g. Hilti HIT-HY 200 V3: #4 2¾", #5 3⅛", #6 3½").
  • Epoxy per anchor: Average of the gap (π ÷ 4 × (hole² − steel²) × embedment) and the hole ⅔ full (⅔ × π ÷ 4 × hole² × embedment)Installers fill the hole about ⅔ full; what the anchor pushes out of the hole is lost, so the real use is between the gap alone and the ⅔ fill — taken as the average of the two. The total is rounded up to a whole fl oz. Waste, if entered, is added on top for rough holes and hard conditions.
  • Drilled hole size (ANSI B212.15): Carbide bit tips (in.): 7/16 0.458–0.468 · ½ 0.520–0.530 · 9/16 0.582–0.592 · ⅝ 0.650–0.660 · 11/16 0.713–0.723 · ¾ 0.775–0.787 · ⅞ 0.905–0.917 · 1 1.030–1.042 · 1⅛ 1.160–1.175 · 1⅜ 1.410–1.425 · 1½ 1.535–1.550A bit drills a little over its name; the hole is taken at the middle of the range (7/16 → 0.463, ⅞ → 0.911, 1½ → 1.5425). A hole size you type that is not a standard bit is used as typed.Fuente
  • Threaded rod steel: d − 5√3 ÷ 16 × pitch: halfway between the outside of the rod and its thread root (d − 5√3 ÷ 8 × pitch) · UNC ⅜-16, ½-13, ⅝-11, ¾-10, ⅞-9, 1-8, 1¼-7Thread geometry (ASME B1.1, H = √3 ÷ 2 × pitch). The epoxy fills the thread grooves, so a rod holds less steel than a solid bar of its size (¾" → 0.6959", ½" → 0.4584"). Rebar uses its nominal size (#10 = 1.270").
  • Extension tube: Past 8" deep: (embedment − 8") × 0.17 fl oz per inch, a new tube every 10 anchorsA mixing nozzle reaches about 8"; deeper holes are filled from the bottom through an extension tube, which holds 0.17 fl oz per inch (the inside of a ⅝" bore: π ÷ 4 × 0.625² = 0.307 in³ per inch) and is replaced every 10 anchors.
  • Cartridges: Sizes in mL as printed, fl oz worked out (mL ÷ 29.5735) · Hilti HIT-HY 200 V3 330 / 500 mL = 11.2 / 16.9 fl oz · DeWalt AC100+ Gold 280 / 825 mL = 9.5 / 27.9 fl ozWhat a cartridge really gives, after the nozzle and the first mix: 9.07 fl oz from the 9.5 oz and 27.29 fl oz from the 28 oz AC100+ Gold. Hilti lists none, so its packs are taken at 96%.
  • Hilti HIT-HY 200 V3: Bits: rod ⅜→7/16 · ½→9/16 · ⅝→¾ · ¾→⅞ · ⅞→1 · 1→1⅛ · 1¼→1⅜ · rebar #3→½ · #4→⅝ · #5→¾ · #6→⅞ · #7→1 · #8→1⅛ · #10→1½ · foil packs 330 and 500 mLHilti Anchor Fastening Technical Guide Ed. 22, Table 38 (threaded rod) and Table 18 (rebar); the same bits in grouted CMU (Masonry Anchor Design Guide 2023, Table 1); ICC-ES ESR-4868 (revised April 2026) §3.2.1 for the 330 / 500 mL packs. Hilti lists a bigger bit for deep embedment (#6 1", #7 1⅛", #8 1¼") — type it if you drill that deep. Hilti's own Volume Calculator is a phone app.Fuente
  • DeWalt AC100+ Gold: Bits: rod ⅜→7/16 · ½→9/16 · ⅝→11/16 · ¾→⅞ · ⅞→1 · 1→1⅛ · 1¼→1⅜ · rebar #3→7/16 · #4→⅝ · #5→¾ · #6→⅞ · #7→1 · #8→1⅛ · #10→1½ · cartridges 280 mL (8478SD-PWR) and 825 mL (8490SD-PWR)DeWalt AC100+ Gold Technical Guide ©2025 rev. K (p. 2 installation, p. 29 ordering), matching ICC-ES ESR-2582 (Feb 2026) Table 9. Approved for rebar used as an anchor (embedment up to about 12 bar diameters), not for post-installed rebar development or splices.Fuente
  • Hole size rule (the cross-check): Bit = anchor + adhesive ring, in 1/16" steps: rod + 1/16" up to ⅝", + ⅛" above · rebar (actual size) + ⅛" · every maker's bit is checked to leave 1/32"–3/16" of ring each sideA cross-check on every maker's bit, and the answer wherever a maker's number cannot be found. Makers may call for a different size — type your hole size if so.
  • Method source: DeWalt Adhesive Anchor Volume EstimatorThe ⅔ fill, the extension tube and the usable cartridge follow it; every number on this page is also worked out by math.Fuente
  • Rebar weights (ASTM A615): #4 0.668 · #5 1.043 · #6 1.502 · #7 2.044 · #8 2.670 lb/ftThe same table the rebar calculator uses: bar area × 3.40 lb/ft per in².Fuente
  • Stock bars: Lapped bars use full stock pieces plus a cut piece; lift bars and cut pieces are packed into stock bars longest firstOffcuts that fit another cut piece are reused — three 6'8" lift bars come out of one 20' bar. Waste, if entered, is added to the stock bar count only.

Resultados guardados

Nada guardado todavía. Toca Guardar para conservar un resultado en este dispositivo.

Block, mortero y grout para un muro de block de concreto, de 4" a 12".