Calculadoras de obra

Calculadora de losa elevada

30.88 CYlosa 12.21 CY + muros de costilla 18.67 CY
2,133.33 ft³ aislamiento · 25 piezas · 204 varillas
Área
989.00 SF
Losa (4")
12.21 CY
Muros de costilla (6" de espesor, 2' 8" de alto)
18.67 CY
Concreto en total
30.88 CY
Peso del concreto (140 lb/ft³)
116,713 lb (58.36 toneladas)
Varilla de los muros de costilla
Varillas (#4 @ 24" a centros)
204 varillas
Pata (ancla + costilla + mitad de la losa), por fuera
38-1/4"
Gancho de 90° G = 12 db + D ÷ 2 + db (D = 6 db = 3")
8"
Cada varilla doblada = pata + G
46-1/4"
Largo total de varilla
786 LF
Peso de #4
525 lb (0.26 toneladas)
Varillas de 20' a comprar
41 varillas
Muros de costilla, largo total
386 LF
DeWalt AC100+ Gold, 27.9 fl oz (4" de empotramiento)
4 cartuchos
Broca · epóxico en total
0.625" · 83.0 fl oz
Malla
Hojas de malla (5' 0" × 10' 0", traslape de 10")
30 hojas
#4 sobre las costillas
Una varilla en cada línea de costilla (12 líneas), con traslapes
424 LF
Traslapes
18 × 25"
Peso de varilla #4
283 lb (0.14 toneladas)
Varillas de 20' 0" a comprar
22 varillas

Estos croquis son para ayudarte a pedir material y cotizar el trabajo rápido. No son planos de ingeniería ni de taller — construye siempre con los planos aprobados del proyecto.

Corte fuera de escala: las alturas se dibujan 6× más altas para que se vean la losa y las costillas. Los largos están a escala y cada cota muestra la medida real.

Losa

Altura

Altura = de lo alto de la losa al terreno. Los niveles aceptan pies y pulgadas o pies decimales (100.25).

Aislamiento

Aislamiento
2,133.33 ft³
Hojas de aislamiento cortadas a 2' 8" de alto (5 × 5 bolsas)
25 piezas
A · 8' 0" × 4' 0" × 32" de alto
25 piezas
Pedir: hojas completas de 4' 0" × 8' 0", cortadas a 2' 8" de alto
25 hojas
· 25 hojas completas
25 hojas
Aislamiento pedido (25 hojas)
2,133.33 ft³
Extra sobre las bolsas (sobrantes)
0.00 ft³
Ver las piezas en 3D▾
A8' 0"4' 0"32"
A: 25 piezas
Ver las cuentas▾
  1. Rib wall height
    rib = height − slab
    3' 0" − 4" = 2' 8"
  2. Slab
    V = L × W × slab
    43' 0" × 23' 0" × 4" = 12.21 CY
  3. Rib walls
    V = rib footprint × rib height
    189.00 SF × 2' 8" = 18.67 CY
  4. Concrete in all
    V = slab + rib walls
    12.21 CY + 18.67 CY = 30.88 CY
  5. Insulation
    V = pocket area × rib height
    800.00 SF × 2' 8" = 2,133.33 ft³
  6. Insulation pieces
    each pocket: whole pieces of the sheet size, cut to the height
    25 pockets = 25
  7. Sheets to order
    full pieces: 1 sheet each; cut pieces packed onto sheets, biggest first, offcuts reused
    25 pieces = 25
  8. Insulation ordered (cross-check)
    each sheet × the height it is ordered at; never less than the pockets
    25 sheets ≥ 2,133.33 ft³ = 2,133.33 ft³
  9. Rib rebar
    each rib line ⌈length ÷ spacing⌉ (+1 inside; the perimeter loop shares corners)
    386' 0" of rib line ÷ 2' 0" = 204
  10. Hook G (ACI 90° standard hook, out to out)
    G = 12 db + D ÷ 2 + db, D = 6 db
    6" + 1-1/2" + 1/2" = 8"
  11. Each rebar (bent bar)
    ℓ = leg + G, leg = dowel + rib height + half the slab + db ÷ 2
    4" + 2' 8" + 2" + 1/4" + 8" = 3' 10-1/4"
  12. Drilled hole (in)
    a carbide bit drills the middle of its ANSI B212.15 range
    5/8" bit: ( 0.650 + 0.660 ) ÷ 2 = 0.6550
  13. Hole volume
    π ÷ 4 × drilled hole² × embedment
    π ÷ 4 × 5/8" ² × 4" = 1.35 in³
  14. Just the gap
    hole − steel (π ÷ 4 × steel² × embedment)
    1.35 in³ − 0.79 in³ = 0.56 in³
  15. Hole ⅔ full
    ⅔ × hole (the instructions say fill the hole about ⅔ full)
    ⅔ × 1.35 in³ = 0.90 in³
  16. Epoxy per anchor
    (gap + ⅔ fill) ÷ 2
    ( 0.56 in³ + 0.90 in³ ) ÷ 2 = 0.73 in³
  17. All anchors
    per anchor × anchors (+ tube), rounded up to a whole fl oz
    0.73 in³ × 204 = 83 fl oz
  18. One cartridge gives
    cartridge less the nozzle and first-mix loss
    27.9 fl oz = 27.29 fl oz
  19. Cartridges
    all anchors ÷ one cartridge, rounded up
    83 fl oz ÷ 27.29 fl oz = 4
  20. Mesh sheet coverage
    c = (sheet width − lap) × (sheet length − lap)
    ( 5' 0" − 10" ) × ( 10' 0" − 10" ) = 38.19 SF
  21. Mesh sheets along the length
    n = ⌈(run − lap) ÷ (sheet − lap)⌉
    ⌈( 43' 0" − 10" ) ÷ ( 10' 0" − 10" )⌉ = 5
  22. Mesh sheets across the width
    n = ⌈(run − lap) ÷ (sheet − lap)⌉
    ⌈( 23' 0" − 10" ) ÷ ( 5' 0" − 10" )⌉ = 6
  23. Mesh sheets
    sheets = along × across
    5 × 6 = 30
  24. Without laps, for comparison
    whole sheets ⌈run ÷ sheet⌉ each way, no laps
    30 with laps − 5 added by laps = 25
  25. Bar along the top of every rib (#4)
    Σ rib lines (along the slope) + laps × lap
    386' 0" + 18 × 2' 1" = 423' 6"

De dónde salen los números

  • Ramp slopes (ADA): Running slope 1:12 at most (1" of rise per foot) · cross slope 1:48 at most · 30" of rise at most per run, then a level landing at least 60" long2010 ADA Standards 405.2, 405.3, 405.6 and 405.7 (U.S. Access Board guide). A walking surface steeper than 1:20 is a ramp. Existing buildings short of room may use 1:10 for 6" of rise or 1:8 for 3". The page warns past 1:12 or 30"; your local code may ask for more.Fuente
  • Raised slab: how it is figured: Slab = L × W × thickness · rib walls and insulation pockets piece by piece × rib heightRib height = total height − slab. Pockets are the clear spaces between rib walls (default 4' × 8'); on a flat slab the odd bit at the end of a row is insulation too (into the last pocket, or a short pocket after one more rib). On a ramp (owner) full pockets are laid from the high end and what is left at the low end is solid concrete, down to 0'0" where the ramp meets grade; where the ramp is lower than the slab it is all concrete. The height changes straight along the length, so every piece uses its height averaged over it (exact for a straight slope). Rib crossings are counted once. Insulation: pieces of the sheet size in plan, tagged A, B … on the piece map, cut to the height (made to order); on a ramp each piece is a block as tall as its low end plus a wedge rising to its high end, or one tapered piece — sizes for the plant. Rib rebar: bars at a spacing, each in a hole drilled into the slab below (the dowel), up to the middle of the slab and bent there into an ACI standard 90° hook (D = 6 db, 12 db past the bend), no laps — ⌈rib line ÷ spacing⌉ per line (+1 on inside lines). Sized out to out the way rebar shops detail them (ACI 315 §3.7, CRSI): leg = dowel + rib height + half the slab + half the bar, hook G = 12 db + D ÷ 2 + db (#4: 8"), bar = leg + G. Use your drawings for rib size, spacing and dowels.
  • Epoxy per anchor: Average of the gap (π ÷ 4 × (hole² − steel²) × embedment) and the hole ⅔ full (⅔ × π ÷ 4 × hole² × embedment)Installers fill the hole about ⅔ full; what the anchor pushes out of the hole is lost, so the real use is between the gap alone and the ⅔ fill — taken as the average of the two. The total is rounded up to a whole fl oz. Waste, if entered, is added on top for rough holes and hard conditions.
  • Drilled hole size (ANSI B212.15): Carbide bit tips (in.): 7/16 0.458–0.468 · ½ 0.520–0.530 · 9/16 0.582–0.592 · ⅝ 0.650–0.660 · 11/16 0.713–0.723 · ¾ 0.775–0.787 · ⅞ 0.905–0.917 · 1 1.030–1.042 · 1⅛ 1.160–1.175 · 1⅜ 1.410–1.425 · 1½ 1.535–1.550A bit drills a little over its name; the hole is taken at the middle of the range (7/16 → 0.463, ⅞ → 0.911, 1½ → 1.5425). A hole size you type that is not a standard bit is used as typed.Fuente
  • Threaded rod steel: d − 5√3 ÷ 16 × pitch: halfway between the outside of the rod and its thread root (d − 5√3 ÷ 8 × pitch) · UNC ⅜-16, ½-13, ⅝-11, ¾-10, ⅞-9, 1-8, 1¼-7Thread geometry (ASME B1.1, H = √3 ÷ 2 × pitch). The epoxy fills the thread grooves, so a rod holds less steel than a solid bar of its size (¾" → 0.6959", ½" → 0.4584"). Rebar uses its nominal size (#10 = 1.270").
  • Extension tube: Past 8" deep: (embedment − 8") × 0.17 fl oz per inch, a new tube every 10 anchorsA mixing nozzle reaches about 8"; deeper holes are filled from the bottom through an extension tube, which holds 0.17 fl oz per inch (the inside of a ⅝" bore: π ÷ 4 × 0.625² = 0.307 in³ per inch) and is replaced every 10 anchors.
  • Cartridges: Sizes in mL as printed, fl oz worked out (mL ÷ 29.5735) · Hilti HIT-HY 200 V3 330 / 500 mL = 11.2 / 16.9 fl oz · DeWalt AC100+ Gold 280 / 825 mL = 9.5 / 27.9 fl ozWhat a cartridge really gives, after the nozzle and the first mix: 9.07 fl oz from the 9.5 oz and 27.29 fl oz from the 28 oz AC100+ Gold. Hilti lists none, so its packs are taken at 96%.
  • Hilti HIT-HY 200 V3: Bits: rod ⅜→7/16 · ½→9/16 · ⅝→¾ · ¾→⅞ · ⅞→1 · 1→1⅛ · 1¼→1⅜ · rebar #3→½ · #4→⅝ · #5→¾ · #6→⅞ · #7→1 · #8→1⅛ · #10→1½ · foil packs 330 and 500 mLHilti Anchor Fastening Technical Guide Ed. 22, Table 38 (threaded rod) and Table 18 (rebar); the same bits in grouted CMU (Masonry Anchor Design Guide 2023, Table 1); ICC-ES ESR-4868 (revised April 2026) §3.2.1 for the 330 / 500 mL packs. Hilti lists a bigger bit for deep embedment (#6 1", #7 1⅛", #8 1¼") — type it if you drill that deep. Hilti's own Volume Calculator is a phone app.Fuente
  • DeWalt AC100+ Gold: Bits: rod ⅜→7/16 · ½→9/16 · ⅝→11/16 · ¾→⅞ · ⅞→1 · 1→1⅛ · 1¼→1⅜ · rebar #3→7/16 · #4→⅝ · #5→¾ · #6→⅞ · #7→1 · #8→1⅛ · #10→1½ · cartridges 280 mL (8478SD-PWR) and 825 mL (8490SD-PWR)DeWalt AC100+ Gold Technical Guide ©2025 rev. K (p. 2 installation, p. 29 ordering), matching ICC-ES ESR-2582 (Feb 2026) Table 9. Approved for rebar used as an anchor (embedment up to about 12 bar diameters), not for post-installed rebar development or splices.Fuente
  • Hole size rule (the cross-check): Bit = anchor + adhesive ring, in 1/16" steps: rod + 1/16" up to ⅝", + ⅛" above · rebar (actual size) + ⅛" · every maker's bit is checked to leave 1/32"–3/16" of ring each sideA cross-check on every maker's bit, and the answer wherever a maker's number cannot be found. Makers may call for a different size — type your hole size if so.
  • Method source: DeWalt Adhesive Anchor Volume EstimatorThe ⅔ fill, the extension tube and the usable cartridge follow it; every number on this page is also worked out by math.Fuente
  • Rebar weights (ASTM A615): #3 0.376 · #4 0.668 · #5 1.043 · #6 1.502 · #7 2.044 · #8 2.670 · #9 3.400 · #10 4.303 · #11 5.313 lb/ftASTM A615 Table 1 nominal weights, as listed on Harris Supply Solutions' "Concrete Reinforcing Bar Products" sheet. Each equals the bar area × 3.40 lb/ft per in² (steel at about 490 lb/ft³): #4 = π × 0.5² ÷ 4 = 0.1963 in² × 3.40 = 0.668 lb/ft.Fuente
  • Welded wire mesh lap: 10 in by default (ACI minimum: one mesh square + 2 in = 8 in for 6×6 mesh) · sheets 5' × 10'ACI 318-19 §25.5.4 (plain welded wire in structural slabs) and ACI 439.5R-18 §6.4 both give one square plus 2 in, as summarized by ASCC (Jan 2021); 10 in is more than that minimum. 6×6-W1.4×W1.4 is the usual minimum temperature mesh on composite deck (SDI). Your engineer may call for a different lap — type it in. Sheets are counted laid the way that takes fewer, with no offcuts reused; counted by area, offcuts are assumed reused, so order extra.Fuente
  • Bar along the top of the ribs (with wire mesh): One continuous #4 along every rib, in the slab: the perimeter loop and every inside rib lineCommon practice when the slab on the ribs is reinforced with wire mesh. Counted on the rib centre lines (lines along a ramp follow the slope), lapped where a line is longer than a stock bar with the ACI Class B lap at 4,000 psi (25" for #4). Corners of the perimeter loop are not lapped extra. Use your drawings.
  • Lap splice (ACI 318-19 Class B): 4,000 psi, Grade 60, uncoated: #3 19" · #4 25" · #5 31" · #6 37" · #7 54" · #8 62" · #9 70" · #10 79" · #11 87"Class B tension lap = 1.3 × ℓd (§25.5.2.1), ℓd from Table 25.4.2.3: fy ÷ (25 λ √f'c) × db for #6 and smaller, ÷ 20 for #7 and larger, rounded up, at least 12". Assumes bars not cast with more than 12" of concrete below them, uncoated, cover ≥ db and spacing ≥ 3 db — usual for a slab grid. Lightweight concrete: λ = 0.75 (longer lap). Same as Table 1.11 of the Dayton Superior Rebar Splicing Handbook (Other bars, Case 1, Class B) at 3,000 and 4,000 psi; at 5,000 psi #4, #6, #8 and #10 come out 1" longer here because they are rounded up. Use the lap on your structural drawings when it is given.Fuente

Resultados guardados

Nada guardado todavía. Toca Guardar para conservar un resultado en este dispositivo.

Una losa elevada se arma sobre aislamiento: muros de costilla de concreto alrededor de bolsas de aislamiento, con la losa colada encima. Aquí sale el concreto de la losa y de los muros de costilla, el aislamiento y el acero.