A raised slab is built up on insulation: rib walls of concrete around insulation pockets, with the slab poured on top. This works out the concrete for the slab and the rib walls, the insulation, and the steel.
Raised slab calculator
30.88 CYslab 12.21 CY + rib walls 18.67 CY
2,133.33 ft³ insulation · 25 pieces · 204 bars
- Area
- 989.00 SF
- Slab (4")
- 12.21 CY
- Rib walls (6" thick, 2' 8" high)
- 18.67 CY
- Concrete in all
- 30.88 CY
- Concrete weight (140 lb/ft³)
- 116,713 lb (58.36 tons)
- Rib walls rebar
- Rebar (#4 @ 24" O.C.)
- 204 bars
- Leg (dowel + rib + half the slab), out to out
- 38-1/4"
- 90° hook G = 12 db + D ÷ 2 + db (D = 6 db = 3")
- 8"
- Each bent bar = leg + G
- 46-1/4"
- Total bar length
- 786 LF
- #4 weight
- 525 lb (0.26 tons)
- 20' bars to buy
- 41 bars
- Rib walls, total length
- 386 LF
- DeWalt AC100+ Gold, 27.9 fl oz (4" embedment)
- 4 cartridges
- Drill bit · epoxy in all
- 0.625" · 83.0 fl oz
- Wire mesh
- Wire mesh sheets (5' 0" × 10' 0", 10" lap)
- 30 sheets
- #4 along the top of the ribs
- One bar on every rib line (12 lines), with laps
- 424 LF
- Laps
- 18 × 25"
- #4 weight
- 283 lb (0.14 tons)
- 20' 0" bars to buy
- 22 bars
These sketches are here to help you order material and price the work quickly. They are not engineered or shop drawings — always build from your approved project drawings.
Section not to scale: heights are drawn 6× taller so the slab and rib walls show. Lengths are to scale, and every dimension shows the real size.
Insulation
- Insulation
- 2,133.33 ft³
- Insulation sheets cut to 2' 8" high (5 × 5 pockets)
- 25 pieces
- A · 8' 0" × 4' 0" × 32" high
- 25 pieces
- Order: full sheets 4' 0" × 8' 0", cut to 2' 8" high
- 25 sheets
- · 25 sheets used whole
- 25 sheets
- Insulation ordered (25 sheets)
- 2,133.33 ft³
- Extra over the pockets (offcuts)
- 0.00 ft³
Show the pieces in 3D▾
Slab
Height
Height = top of slab to grade. Elevations take feet and inches or decimal feet (100.25).
Insulation
- Insulation
- 2,133.33 ft³
- Insulation sheets cut to 2' 8" high (5 × 5 pockets)
- 25 pieces
- A · 8' 0" × 4' 0" × 32" high
- 25 pieces
- Order: full sheets 4' 0" × 8' 0", cut to 2' 8" high
- 25 sheets
- · 25 sheets used whole
- 25 sheets
- Insulation ordered (25 sheets)
- 2,133.33 ft³
- Extra over the pockets (offcuts)
- 0.00 ft³
Show the pieces in 3D▾
Show the math▾
- Rib wall heightrib = height − slab3' 0" − 4" = 2' 8"
- SlabV = L × W × slab43' 0" × 23' 0" × 4" = 12.21 CY
- Rib wallsV = rib footprint × rib height189.00 SF × 2' 8" = 18.67 CY
- Concrete in allV = slab + rib walls12.21 CY + 18.67 CY = 30.88 CY
- InsulationV = pocket area × rib height800.00 SF × 2' 8" = 2,133.33 ft³
- Insulation pieceseach pocket: whole pieces of the sheet size, cut to the height25 pockets = 25
- Sheets to orderfull pieces: 1 sheet each; cut pieces packed onto sheets, biggest first, offcuts reused25 pieces = 25
- Insulation ordered (cross-check)each sheet × the height it is ordered at; never less than the pockets25 sheets ≥ 2,133.33 ft³ = 2,133.33 ft³
- Rib rebareach rib line ⌈length ÷ spacing⌉ (+1 inside; the perimeter loop shares corners)386' 0" of rib line ÷ 2' 0" = 204
- Hook G (ACI 90° standard hook, out to out)G = 12 db + D ÷ 2 + db, D = 6 db6" + 1-1/2" + 1/2" = 8"
- Each rebar (bent bar)ℓ = leg + G, leg = dowel + rib height + half the slab + db ÷ 24" + 2' 8" + 2" + 1/4" + 8" = 3' 10-1/4"
- Drilled hole (in)a carbide bit drills the middle of its ANSI B212.15 range5/8" bit: ( 0.650 + 0.660 ) ÷ 2 = 0.6550
- Hole volumeπ ÷ 4 × drilled hole² × embedmentπ ÷ 4 × 5/8" ² × 4" = 1.35 in³
- Just the gaphole − steel (π ÷ 4 × steel² × embedment)1.35 in³ − 0.79 in³ = 0.56 in³
- Hole ⅔ full⅔ × hole (the instructions say fill the hole about ⅔ full)⅔ × 1.35 in³ = 0.90 in³
- Epoxy per anchor(gap + ⅔ fill) ÷ 2( 0.56 in³ + 0.90 in³ ) ÷ 2 = 0.73 in³
- All anchorsper anchor × anchors (+ tube), rounded up to a whole fl oz0.73 in³ × 204 = 83 fl oz
- One cartridge givescartridge less the nozzle and first-mix loss27.9 fl oz = 27.29 fl oz
- Cartridgesall anchors ÷ one cartridge, rounded up83 fl oz ÷ 27.29 fl oz = 4
- Mesh sheet coveragec = (sheet width − lap) × (sheet length − lap)( 5' 0" − 10" ) × ( 10' 0" − 10" ) = 38.19 SF
- Mesh sheets along the lengthn = ⌈(run − lap) ÷ (sheet − lap)⌉⌈( 43' 0" − 10" ) ÷ ( 10' 0" − 10" )⌉ = 5
- Mesh sheets across the widthn = ⌈(run − lap) ÷ (sheet − lap)⌉⌈( 23' 0" − 10" ) ÷ ( 5' 0" − 10" )⌉ = 6
- Mesh sheetssheets = along × across5 × 6 = 30
- Without laps, for comparisonwhole sheets ⌈run ÷ sheet⌉ each way, no laps30 with laps − 5 added by laps = 25
- Bar along the top of every rib (#4)Σ rib lines (along the slope) + laps × lap386' 0" + 18 × 2' 1" = 423' 6"
Where the numbers come from
- Ramp slopes (ADA): Running slope 1:12 at most (1" of rise per foot) · cross slope 1:48 at most · 30" of rise at most per run, then a level landing at least 60" long2010 ADA Standards 405.2, 405.3, 405.6 and 405.7 (U.S. Access Board guide). A walking surface steeper than 1:20 is a ramp. Existing buildings short of room may use 1:10 for 6" of rise or 1:8 for 3". The page warns past 1:12 or 30"; your local code may ask for more.Source
- Raised slab: how it is figured: Slab = L × W × thickness · rib walls and insulation pockets piece by piece × rib heightRib height = total height − slab. Pockets are the clear spaces between rib walls (default 4' × 8'); on a flat slab the odd bit at the end of a row is insulation too (into the last pocket, or a short pocket after one more rib). On a ramp (owner) full pockets are laid from the high end and what is left at the low end is solid concrete, down to 0'0" where the ramp meets grade; where the ramp is lower than the slab it is all concrete. The height changes straight along the length, so every piece uses its height averaged over it (exact for a straight slope). Rib crossings are counted once. Insulation: pieces of the sheet size in plan, tagged A, B … on the piece map, cut to the height (made to order); on a ramp each piece is a block as tall as its low end plus a wedge rising to its high end, or one tapered piece — sizes for the plant. Rib rebar: bars at a spacing, each in a hole drilled into the slab below (the dowel), up to the middle of the slab and bent there into an ACI standard 90° hook (D = 6 db, 12 db past the bend), no laps — ⌈rib line ÷ spacing⌉ per line (+1 on inside lines). Sized out to out the way rebar shops detail them (ACI 315 §3.7, CRSI): leg = dowel + rib height + half the slab + half the bar, hook G = 12 db + D ÷ 2 + db (#4: 8"), bar = leg + G. Use your drawings for rib size, spacing and dowels.
- Epoxy per anchor: Average of the gap (π ÷ 4 × (hole² − steel²) × embedment) and the hole ⅔ full (⅔ × π ÷ 4 × hole² × embedment)Installers fill the hole about ⅔ full; what the anchor pushes out of the hole is lost, so the real use is between the gap alone and the ⅔ fill — taken as the average of the two. The total is rounded up to a whole fl oz. Waste, if entered, is added on top for rough holes and hard conditions.
- Drilled hole size (ANSI B212.15): Carbide bit tips (in.): 7/16 0.458–0.468 · ½ 0.520–0.530 · 9/16 0.582–0.592 · ⅝ 0.650–0.660 · 11/16 0.713–0.723 · ¾ 0.775–0.787 · ⅞ 0.905–0.917 · 1 1.030–1.042 · 1⅛ 1.160–1.175 · 1⅜ 1.410–1.425 · 1½ 1.535–1.550A bit drills a little over its name; the hole is taken at the middle of the range (7/16 → 0.463, ⅞ → 0.911, 1½ → 1.5425). A hole size you type that is not a standard bit is used as typed.Source
- Threaded rod steel: d − 5√3 ÷ 16 × pitch: halfway between the outside of the rod and its thread root (d − 5√3 ÷ 8 × pitch) · UNC ⅜-16, ½-13, ⅝-11, ¾-10, ⅞-9, 1-8, 1¼-7Thread geometry (ASME B1.1, H = √3 ÷ 2 × pitch). The epoxy fills the thread grooves, so a rod holds less steel than a solid bar of its size (¾" → 0.6959", ½" → 0.4584"). Rebar uses its nominal size (#10 = 1.270").
- Extension tube: Past 8" deep: (embedment − 8") × 0.17 fl oz per inch, a new tube every 10 anchorsA mixing nozzle reaches about 8"; deeper holes are filled from the bottom through an extension tube, which holds 0.17 fl oz per inch (the inside of a ⅝" bore: π ÷ 4 × 0.625² = 0.307 in³ per inch) and is replaced every 10 anchors.
- Cartridges: Sizes in mL as printed, fl oz worked out (mL ÷ 29.5735) · Hilti HIT-HY 200 V3 330 / 500 mL = 11.2 / 16.9 fl oz · DeWalt AC100+ Gold 280 / 825 mL = 9.5 / 27.9 fl ozWhat a cartridge really gives, after the nozzle and the first mix: 9.07 fl oz from the 9.5 oz and 27.29 fl oz from the 28 oz AC100+ Gold. Hilti lists none, so its packs are taken at 96%.
- Hilti HIT-HY 200 V3: Bits: rod ⅜→7/16 · ½→9/16 · ⅝→¾ · ¾→⅞ · ⅞→1 · 1→1⅛ · 1¼→1⅜ · rebar #3→½ · #4→⅝ · #5→¾ · #6→⅞ · #7→1 · #8→1⅛ · #10→1½ · foil packs 330 and 500 mLHilti Anchor Fastening Technical Guide Ed. 22, Table 38 (threaded rod) and Table 18 (rebar); the same bits in grouted CMU (Masonry Anchor Design Guide 2023, Table 1); ICC-ES ESR-4868 (revised April 2026) §3.2.1 for the 330 / 500 mL packs. Hilti lists a bigger bit for deep embedment (#6 1", #7 1⅛", #8 1¼") — type it if you drill that deep. Hilti's own Volume Calculator is a phone app.Source
- DeWalt AC100+ Gold: Bits: rod ⅜→7/16 · ½→9/16 · ⅝→11/16 · ¾→⅞ · ⅞→1 · 1→1⅛ · 1¼→1⅜ · rebar #3→7/16 · #4→⅝ · #5→¾ · #6→⅞ · #7→1 · #8→1⅛ · #10→1½ · cartridges 280 mL (8478SD-PWR) and 825 mL (8490SD-PWR)DeWalt AC100+ Gold Technical Guide ©2025 rev. K (p. 2 installation, p. 29 ordering), matching ICC-ES ESR-2582 (Feb 2026) Table 9. Approved for rebar used as an anchor (embedment up to about 12 bar diameters), not for post-installed rebar development or splices.Source
- Hole size rule (the cross-check): Bit = anchor + adhesive ring, in 1/16" steps: rod + 1/16" up to ⅝", + ⅛" above · rebar (actual size) + ⅛" · every maker's bit is checked to leave 1/32"–3/16" of ring each sideA cross-check on every maker's bit, and the answer wherever a maker's number cannot be found. Makers may call for a different size — type your hole size if so.
- Method source: DeWalt Adhesive Anchor Volume EstimatorThe ⅔ fill, the extension tube and the usable cartridge follow it; every number on this page is also worked out by math.Source
- Rebar weights (ASTM A615): #3 0.376 · #4 0.668 · #5 1.043 · #6 1.502 · #7 2.044 · #8 2.670 · #9 3.400 · #10 4.303 · #11 5.313 lb/ftASTM A615 Table 1 nominal weights, as listed on Harris Supply Solutions' "Concrete Reinforcing Bar Products" sheet. Each equals the bar area × 3.40 lb/ft per in² (steel at about 490 lb/ft³): #4 = π × 0.5² ÷ 4 = 0.1963 in² × 3.40 = 0.668 lb/ft.Source
- Welded wire mesh lap: 10 in by default (ACI minimum: one mesh square + 2 in = 8 in for 6×6 mesh) · sheets 5' × 10'ACI 318-19 §25.5.4 (plain welded wire in structural slabs) and ACI 439.5R-18 §6.4 both give one square plus 2 in, as summarized by ASCC (Jan 2021); 10 in is more than that minimum. 6×6-W1.4×W1.4 is the usual minimum temperature mesh on composite deck (SDI). Your engineer may call for a different lap — type it in. Sheets are counted laid the way that takes fewer, with no offcuts reused; counted by area, offcuts are assumed reused, so order extra.Source
- Bar along the top of the ribs (with wire mesh): One continuous #4 along every rib, in the slab: the perimeter loop and every inside rib lineCommon practice when the slab on the ribs is reinforced with wire mesh. Counted on the rib centre lines (lines along a ramp follow the slope), lapped where a line is longer than a stock bar with the ACI Class B lap at 4,000 psi (25" for #4). Corners of the perimeter loop are not lapped extra. Use your drawings.
- Lap splice (ACI 318-19 Class B): 4,000 psi, Grade 60, uncoated: #3 19" · #4 25" · #5 31" · #6 37" · #7 54" · #8 62" · #9 70" · #10 79" · #11 87"Class B tension lap = 1.3 × ℓd (§25.5.2.1), ℓd from Table 25.4.2.3: fy ÷ (25 λ √f'c) × db for #6 and smaller, ÷ 20 for #7 and larger, rounded up, at least 12". Assumes bars not cast with more than 12" of concrete below them, uncoated, cover ≥ db and spacing ≥ 3 db — usual for a slab grid. Lightweight concrete: λ = 0.75 (longer lap). Same as Table 1.11 of the Dayton Superior Rebar Splicing Handbook (Other bars, Case 1, Class B) at 3,000 and 4,000 psi; at 5,000 psi #4, #6, #8 and #10 come out 1" longer here because they are rounded up. Use the lap on your structural drawings when it is given.Source